2020
ANGS-04-U-BAL-GE-001 Well Testing & Appraisal WSCC 040 17 BA Decision Notice (2)
View PDFANGS-04-U-BAL-RP-001 Well Testing and Appraisal WSCC 040 17 BA Committee Report
View PDFANGS-04-U-BAL-RP-002 Condition 7 Discharge Balcombe 20180514 Rev 1 (2)
View PDFANGS-04-U-BAL-RP-003 Condition 8 661913 Rev06 15082018
View PDFANGS-04-U-BAL-RP-004 Condition 9 Discharge Balcombe 20180514 Rev 1 (1)
View PDFANGS-04-U-BAL-RP-005 Condition 10 & 17 Lighting & Bat 17082018
View PDFANGS-04-U-BAL-RP-006 Condition 11 Discharge Traffic Management Plan 27092018
View PDFANGS-04-U-BAL-RP-007 Condition 15 Noise Manangement Plan 20082018
View PDFANGS-04-U-BAL-RP-008 Condition 18 Discharge Restoration 25042018
View PDFANGS-04-U-BAL-RP-009 Condition 18 Discharge Restoration Plan 18052018
View PDFANGS-04-U-BAL-RP-010 Condition 19 Discharge Security 17052018
View PDFANGS-04-U-BAL-RP-011 Condition 21 Discharge Community Liason Group 21052018
View PDFANGS-04-U-BAL-RP-012 Eclipse Lighting Plan18092018
View PDFEPR Compliance Assessment Report – Pre-operational condition 5 sign off WEBSITE
View PDFGGS1700 PO05 Vapour Recovery Plan_V4_Website2
View PDFAngus Energy is committed to supplying all relevant and non-proprietary data to residents, investors, and other stakeholders regarding operations at Balcombe Oil Site. The company aims to be fully transparent at Balcombe and beyond, and is pleased to present the documentation to interested parties. As such, the company publishes below all planning discharge documents relating to the Autumn 2018 7-day well test that was carried out on the Balcombe 2Z well. Furthermore, copies of the vapour recovery plan and corresponding Compliance Assessment Report are also provided. Names and contact details have been redacted.